Campbell Road Bridge paving may begin Tuesday

A list of updates to the city's construction projects was posted to Facebook Friday.

Construction continues throughout Smyrna. Friday afternoon the city posted an updated list of projects and their progress to its Facebook page:

Campbell Road Bridge – Campbell Road Bridge remains at 90 percent completion. The bridge contractor indicates he will be finished with the bridge this week as the parapet wall fencing is being installed, bridge deck grooving is being completed and bollards between the roadway and sidewalk are being installed. Road grading and curb work on the southwest side of the bridge is complete and ready for asphalt. The contractor is scheduled to work Saturday to complete road grading and curb work on the northeast side of the bridge. Depending upon progress over the weekend and weather next week, paving may start Tuesday. 

South Cobb Drive Improvement Project - The South Cobb Drive improvement project remains at about 95 percent complete. The contractor addressed the final punch list items and South Cobb paving remains to be completed.

Find out what's happening in Smyrna-Viningswith free, real-time updates from Patch.

Atlanta Road Trail – The Atlanta Road Trail project is approximately 85 percent complete. The signal contractor will be working on the pedestrian signals at the Creatwood intersection next week.

Atlanta Road LCI Streetscape Project – The contractor for the Atlanta Road streetscape project is now working in the block between Village Green Circle and Powder Springs Street.

Find out what's happening in Smyrna-Viningswith free, real-time updates from Patch.

Paving Work at Concord - Street paving resumed this week on Concord Road.