Politics & Government

Smyrna-Vinings Road Work Update

Avoid gridlock and construction delays this weekend and next week.

Traffic in the following areas will be affected by continuing road improvements between Saturday and next Friday, according to the office of District 2 Commissioner Bob Ott:

Paper Mill Road Bridge Replacement

Paper Mill Road Bridge at Sope Creek is closed through Oct. 25, 2013. 
The new bridge will include a six foot sidewalk on the south side, providing access to National Park Service trails. A signed detour route will be provided during construction. 

Find out what's happening in Smyrna-Viningswith free, real-time updates from Patch.

Now that school is in session expect extended delays on Lower Roswell Road (Detour Route).  Plan for alternate routes during these hours. See attached map.

Paper Mill Road at Sope Creek  – Saturday, Sept. 21, through Friday, Sept. 27
The contractor will continue work on the bridge deck and water line installation. Utilities will be relocating services.

Find out what's happening in Smyrna-Viningswith free, real-time updates from Patch.

Lower Roswell Road Construction

 Contractor is not planning to work this weekend – Sept. 21 and 22

Davidson Road to Willow Point Parkway – Monday, Sept. 23, through Friday, Sept. 27
This section of Lower Roswell Road is substantially complete. Contractor is working on punch list.

Willow Point Parkway to Timber Ridge Road – Monday, Sept. 23 through Friday, Sept. 27
Expect periodic lane closures from 9 a.m. to 4 p.m. between Willow Point Parkway and Timber Ridge Road with one lane remaining open. The contractor will continue grading, wall construction and work at roundabout. Utility relocations should not affect your service. EXPECT DELAYS.

Little Willeo Road Sidewalks Construction

The contractor is not planning to work this weekend – Sept. 21 and 22

Karls Gate Drive to Lake Fjord Pass – Monday, Sept. 23, through Friday, Sept. 27
Expect intermittent lane closures from 9 a.m. to 4 p.m. with one lane remaining open at all times. Project is substantially complete. Contractor will be working on punch list including final grading and grassing.   

Concord Road Construction – City of Smyrna

The contractor is not planning to work this weekend – Sept. 21 and 22    

South Cobb Drive to Atlanta Road – Monday, Sept. 23, through Friday, Sept. 27
Expect intermittent lane closures from 9 a.m. to 4 p.m. with one lane remaining open in each direction at all times. The Evelyn Street intersection with Concord Road has been permanently closed.

Roswell Road (SR120) Construction - GDOT
Providence Road to Robinson Road – This GDOT project will require periodic lane closures from 9 a.m. to 4 p.m. with one lane remaining open in each direction at all times. EXPECT DELAYS.

Road Resurfacing

Asphalt paving operations are scheduled for next week, Monday, Sept. 23, through Friday, Sept. 27** on the following roads. One lane will be open at all timesEXPECT DELAYS.

  • Night Work – Lower Roswell Road from Roswell Road to South Marietta Parkway.

 ** The above scheduled work is subject to change due to weather or construction progress.